Construction project of Henan Ruzhou Gangli New Materials' 1,500 tons per hour fine aggregate production line

Mine rock quality: Limestone  Project capacity: 1,500 tons per hour  Project address: Pingdingshan City, Henan Province  Construction form: EPCO  Project status: Put into production  Project features: Centralized closure, tank storage and loading; DCS automatic integrated control; One-card intelligent sales; Complete dust removal system with ultra-low emissions; Green, environmental protection, intelligent and efficient.
Construction Project of 6,000 Tons Per Hour Fine Aggregate Production Line of Zigang Mining in Jingmen, Hubei

Mine rock quality: Limestone
Project capacity: 6,000 tons per hour
Project address: Jingmen City, Hubei Province
Construction form: EPC
Project status: Put into production
Project features: Built along the mountain, dual lines operate independently; Centralized material storage and loading; DCS automatic integrated control; One-card intelligent sales; Complete dust removal system with ultra-low emissions; Green, environmental protection, intelligent, and efficient.
Construction project of a 2000-ton/hour high-quality aggregate production line of Guangxi Hezhou Zhongzi Holding Group

Mine rock quality: Limestone
Project capacity: 2000 tons per hour
Project address: Hezhou City, Guangxi Province
Construction form: EPC
Project status: Put into production
Project features: Built along the mountain, with a large terrain difference and a short production line; Storage of materials in the workshop and manual loading; Supporting calcium powder production line, garden-style office area; DCS automatic integrated control; Complete dust removal system for ultra-low emissions; Green, environmental protection, intelligent and efficient. 
Construction project of 3000 tons per hour high-quality aggregate production line of Henan Yuzhou Pinghe Building Materials

Mine rock quality: Limestone
Project capacity: 3000 tons per hour
Project address: Yuzhou City, Henan Province
Construction form: EPC
Project status: Put into production
Project features: Single machine super-large output production line; Concentrated equipment, all enclosed; DCS automatic integrated control; One-card intelligent sales; Complete dust removal system with ultra-low emissions; Green, environmental protection, intelligent, and efficient.
05
"—
07
06
08
"—
Shandong Jining Jiaxiang City Investment 2,000 tons per hour high-quality aggregate production line construction project

Mine stone quality: Limestone Project capacity: 2,000 tons per hour Project address: Jining City, Shandong Province Construction form: EPC Project status: Put into production Project features: Construction on flat ground far from the mine; Separation of production and office; Large reserves of raw material warehouse and finished product warehouse; DCS automated integrated control; One-card intelligent sales; Complete dust removal system for ultra-low emissions; Green, environmentally friendly, intelligent and efficient.
Construction project of Anhui Huaibei Tongming Mining's 3,000 tons per hour high-quality aggregate production line

Mine rock quality: Limestone
Project capacity: 8 million tons/year
Project address: Huaibei City, Anhui Province
Construction form: EPC
Project status: Put into production
Project features: High separation of earth and stone, simultaneous production of common materials, DCS automatic integrated control, one-card intelligent sales system, super-large capacity storage of material storage workshop, intelligent and efficient corridor loading, short process flow, complete dust removal system with ultra-low emissions, multi-point power distribution centralized control, green, environmental protection, intelligent and efficient.
Construction project of 2000 tons per hour high-quality aggregate production line of Luqiang Building Materials in Zoucheng, Shandong Province

Mine rock quality: Limestone
Project capacity: 2000 tons per hour
Project address: Zoucheng City, Shandong Province
Construction form: EPC
Project status: Put into production
Project features: Built along the mountain, with a large terrain difference and a short production line; Centralized and closed, tank storage and loading; DCS automatic integrated control; One-card intelligent sales; Complete dust removal system for ultra-low emissions; Provincial-level green mine.
Construction project of 2,000 tons per hour high-quality aggregate production line of Fangxin Building Materials in Yuzhou, Henan Province

Mine rock quality: Limestone
Project capacity: 2,000 tons per hour
Project address: Yuzhou City, Henan Province
Construction form: EPC
Project status: Put into production
Project features: Built along the mountain, with large terrain difference and short production line; Centralized and closed, tank storage and loading; DCS automatic integrated control; One-card intelligent sales; Complete dust removal system with ultra-low emissions; Green, environmental protection, intelligent and efficient.
09
11
10
"—
12
Construction project of 4,000 tons per hour high-quality aggregate production line of Henan Yuzhou Xinji Building Materials

Mine rock quality: Limestone Project capacity: 4,000 tons per hour Project address: Yuzhou City, Henan Province Construction form: EPC Project status: Put into production Project features: Multiple crushing units to avoid production suspension due to faults; Fully enclosed, tank storage and loading; DCS automatic integrated control; One-card intelligent sales; Complete dust removal system with ultra-low emissions; Green, environmental-friendly, intelligent and efficient.
Anhui Suzhou Gangli Longshan 1,000 tons per hour fine aggregate production line construction project

Mine stone quality: Limestone
Project capacity: 1,000 tons per hour
Project address: Suzhou City, Anhui Province
Construction form: EPCO
Project status: Put into production
Project features: Centralized and closed; Ultra-large reserve workshop, manual loading; DCS automatic integrated control; Complete dust removal system ultra-low emissions; Green, environmental protection, intelligent, efficient; Provincial-level green mine.
Construction Project of 2,000 Tons Per Hour Fine Aggregate Production Line of Donggang Urban Investment in Rizhao, Shandong

Mine rock quality: Granite
Project capacity: 2,000 tons per hour
Project address: Rizhao City, Shandong Province
Contracting form: EPC
Project status: Put into production
Project features: Built along the mountain, with a large terrain difference and a short production line; Storage in the plant and manual loading; Hard rock production line, jaw crusher + cone crusher; DCS automatic integrated control; Complete dust removal system with ultra-low emissions; Green, environmentally friendly, intelligent and efficient.
Construction Project of 1500 Tons Per Hour Fine Aggregate Production Line of Xingyunyuan Building Materials in Zaozhuang, Shandong

Mine rock quality: Limestone
Project capacity: 1500 tons per hour
Project address: Zaozhuang City, Shandong Province
Construction form: EPCO
Project status: Put into production
Project features: Construction on flat ground far from the mine; Centralized sealing, tank storage and loading; DCS automated integrated control; Intelligent sales with one-card system; Complete dust removal system with ultra-low emissions; Green, environmental protection, intelligent and efficient.